In Haryana Urban Dev. Authority and Ors. Vs. Orchid Infrastructure Developers P. Ltd., the Respondent filed a suit for declaration with consequential relief as against the Appellants with regard to rejection of bid relating to the commercial tower when the bid submitted by the Respondent was the highest. Plaintiff questioned the rejection of the bid. The question before the court was -
(i) Whether there being no concluded contract in absence of acceptance of bid and issuance of allotment letter, suit could be said to be maintainable for declaratory relief and mandatory injunction sought by Plaintiff
(ii)  Whether Administrator had rejected bid in illegal or arbitrary manner

Held, while allowing the appeal:

(i) The Respondent prayed for a declaration that rejection of the bid was illegal. Merely by that, Plaintiff could not have become entitled for consequential mandatory injunction for issuance of formal letter of allotment. Court while exercising judicial review could not have accepted the bid. The bid had never been accepted by concerned authorities. It was not a case of cancellation of bid after being accepted. Thus even assuming as per Plaintiff's case that the Administrator was not equipped with the power and the Chief Administrator had the power to accept or refuse the bid, there had been no decision by the Chief Administrator. Thus the suit, in the form it was filed, was not maintainable for relief sought in view of the fact that there was no concluded contract in the absence of allotment letter being issued to the Plaintiff, which was a sine qua non for filing the civil suit.

(ii) It is a settled law that the highest bidder has no vested right to have the auction concluded in his favour. The Government or its authority could validly retain power to accept or reject the highest bid in the interest of public revenue. There was no right acquired and no vested right accrued in favour of the Respondent merely because his bid amount was highest and had deposited 10% of the bid amount.

(iii) In the absence of a concluded contract, i.e. in the absence of allotment letter and acceptance of highest bid, the suit by the Respondent was wholly misconceived. Even if non-acceptance of the bid was by an incompetent authority, the court had no power to accept the bid and to direct the allotment letter to be issued. Merely on granting the declaration which was sought that rejection was illegal and arbitrary and by incompetent authority, further relief of mandatory injunction could not have been granted, on the basis of findings recorded, to issue the allotment letter, as it would then become necessary to forward the bid to competent authority-Chief Administrator-for its acceptance, if at all it was required.




Comments

Popular posts from this blog

MACT - Permanent disability - calculate - compensation - Supreme Court - Part 2

1) C. K. Subramonia Iyer vs. T. Kunhikuttan Nair - AIR 1970 SC 376 2) R. D. Hattangadi vs. Pest Control (India) Ltd. - 1995 (1) SCC 551 3) Baker vs. Willoughby - 1970 AC 467 4) Arvind Kumar Mishra v. New India Assurance Co.Ltd. - 2010(10) SCALE 298 5) Yadava Kumar v. D.M., National Insurance Co. Ltd. - 2010 (8) SCALE 567) 5. The heads under which compensation is awarded in personal injury cases are the following : Pecuniary damages (Special Damages) (i) Expenses relating to treatment, hospitalization, medicines, transportation, nourishing food, and miscellaneous expenditure. (ii) Loss of earnings (and other gains) which the injured would have made had he not been injured, comprising : (a) Loss of earning during the period of treatment; (b) Loss of future earnings on account of permanent disability. (iii) Future medical expenses. Non-pecuniary damages (General Damages) (iv) Damages for pain, suffering and trauma as a consequence of the injuries. (v) Loss of ...

Full & Final payment - No dues certificate - end of contract

Whether after the contract comes to an end by completion of the contract work and acceptance of the final bill in full and final satisfaction and after issuance a `No Due Certificate' by the contractor Supreme Court of India Supreme Court of India R.L. Kalathia & Co. vs State Of Gujarat on 14 January, 2011 Author: P Sathasivam Bench: P. Sathasivam, B.S. Chauhan IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 3245 OF 2003 R.L. Kalathia & Co Appellant(s) Versus State of Gujarat .... Respondent(s) JUDGMENT P. Sathasivam, J. 1) This appeal is directed against the judgment and final order dated 07.10.2002 passed by the Division Bench of the High Court of Gujarat whereby the High Court set aside the judgment and decree dated 14.12.1982 passed by the Civil Judge, (S.D.), Jamnagar directing the State Government to pay a sum of Rs.2,27,758/- with costs and interest and dismissed the Civil Suit as well as cross objections filed by the a...

Private Colleges Cannot Withhold Student’s Certificates For Payment Of Amount

In a significant judgement, the , has held that private self financing Colleges cannot withhold certificates of students, for payment of amount. The practise of withholding the certificates, and non-issuance of transfer certificate to students, to coerce them into meeting unconscionable demands like paying entire course fee for leaving the course midway, or to force them to serve the institution after completion of course, etc is very rampant. In clear unambiguous terms, the Court has held that such practise is illegal and opposed to public policy. Often faced with the supreme bargaining position of the Colleges, the students often execute bonds authorising colleges to do so. But, such bonds have no validity in the eyes of law. It was held that :- “The agreements obtained by the College from petitioners authorising them to withhold the certificates of the petitioners cannot be accepted as an approved social conduct and the same, in that sense, is unethical. Further, agreements of tha...