IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.958 OF 2010
Prem Nath Bali ……Appellant(s)
VERSUS
Registrar, High Court of
Delhi & Anr. ……Respondent(s)


29) One cannot dispute in this case that the suspension period was unduly long. We also find that the delay in completion of the departmental proceedings was not wholly attributable to the appellant but it was equally attributable to the respondents as well. Due to such unreasonable delay, the appellant naturally suffered a lot because he and his family had to survive only on suspension allowance for a long period of 9 years.

30) We are constrained to observe as to why the departmental proceeding, which involved only one charge and that too uncomplicated, have taken more than 9 years to conclude the departmental inquiry. No justification was forthcoming from the respondents’ side to explain the undue delay in completion of the departmental inquiry except to throw blame on the appellant's conduct which we feel, was not fully justified.

31) Time and again, this Court has emphasized that it is the duty of the employer to ensure that the departmental inquiry initiated against the delinquent employee is concluded within the shortest possible time by taking priority measures. In cases where the delinquent is placed under suspension during the pendency of such inquiry then it becomes all the more imperative for the employer to ensure that the inquiry is concluded in the shortest possible time to avoid any inconvenience, loss and prejudice to the rights of the delinquent employee.

32) As a matter of experience, we often notice that after completion of the inquiry, the issue involved therein does not come to an end because if the findings of the inquiry proceedings have gone against the delinquent employee, he invariably pursues the issue in Court to ventilate his grievance, which again consumes time for its final conclusion.

33) Keeping these factors in mind, we are of the considered opinion that every employer (whether State or private) must make sincere endeavor to conclude the departmental inquiry proceedings once initiated against the delinquent employee within a reasonable time by giving priority to such proceedings and as far as possible it should be concluded within six months as an outer limit. Where it is not possible for the employer to conclude due to certain unavoidable causes arising in the proceedings within the time frame then efforts should be made to conclude within reasonably extended period depending upon the cause and the nature of inquiry but not more than a year.

Comments

Popular posts from this blog

MACT - Permanent disability - calculate - compensation - Supreme Court - Part 2

1) C. K. Subramonia Iyer vs. T. Kunhikuttan Nair - AIR 1970 SC 376 2) R. D. Hattangadi vs. Pest Control (India) Ltd. - 1995 (1) SCC 551 3) Baker vs. Willoughby - 1970 AC 467 4) Arvind Kumar Mishra v. New India Assurance Co.Ltd. - 2010(10) SCALE 298 5) Yadava Kumar v. D.M., National Insurance Co. Ltd. - 2010 (8) SCALE 567) 5. The heads under which compensation is awarded in personal injury cases are the following : Pecuniary damages (Special Damages) (i) Expenses relating to treatment, hospitalization, medicines, transportation, nourishing food, and miscellaneous expenditure. (ii) Loss of earnings (and other gains) which the injured would have made had he not been injured, comprising : (a) Loss of earning during the period of treatment; (b) Loss of future earnings on account of permanent disability. (iii) Future medical expenses. Non-pecuniary damages (General Damages) (iv) Damages for pain, suffering and trauma as a consequence of the injuries. (v) Loss of ...

Full & Final payment - No dues certificate - end of contract

Whether after the contract comes to an end by completion of the contract work and acceptance of the final bill in full and final satisfaction and after issuance a `No Due Certificate' by the contractor Supreme Court of India Supreme Court of India R.L. Kalathia & Co. vs State Of Gujarat on 14 January, 2011 Author: P Sathasivam Bench: P. Sathasivam, B.S. Chauhan IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 3245 OF 2003 R.L. Kalathia & Co Appellant(s) Versus State of Gujarat .... Respondent(s) JUDGMENT P. Sathasivam, J. 1) This appeal is directed against the judgment and final order dated 07.10.2002 passed by the Division Bench of the High Court of Gujarat whereby the High Court set aside the judgment and decree dated 14.12.1982 passed by the Civil Judge, (S.D.), Jamnagar directing the State Government to pay a sum of Rs.2,27,758/- with costs and interest and dismissed the Civil Suit as well as cross objections filed by the a...

Private Colleges Cannot Withhold Student’s Certificates For Payment Of Amount

In a significant judgement, the , has held that private self financing Colleges cannot withhold certificates of students, for payment of amount. The practise of withholding the certificates, and non-issuance of transfer certificate to students, to coerce them into meeting unconscionable demands like paying entire course fee for leaving the course midway, or to force them to serve the institution after completion of course, etc is very rampant. In clear unambiguous terms, the Court has held that such practise is illegal and opposed to public policy. Often faced with the supreme bargaining position of the Colleges, the students often execute bonds authorising colleges to do so. But, such bonds have no validity in the eyes of law. It was held that :- “The agreements obtained by the College from petitioners authorising them to withhold the certificates of the petitioners cannot be accepted as an approved social conduct and the same, in that sense, is unethical. Further, agreements of tha...