Skip to main content

If clause for damages present, Party entitled to reasonable compensation whether or not actual loss occurred

High Court of Delhi

Mahanagar Telephone Nigam Limited v. Haryana Telecom Limited

MANU/DE/1072/2017

21.04.2017

Arbitration

Party complaining breach of contract is entitled to reasonable compensation whether or not actual loss is proved to have been caused

Mahanagar Telephone Nigam Limited ('MTNL') has filed present petition under Section 34 of Arbitration & Conciliation Act, 1996 challenging an Award dated 12th March, 2003 passed by Arbitral Tribunal ('AT') in disputes between MTNL and Respondent, Haryana Telecom Limited ('HTL'). AT held that, since MTNL failed to prove actual loss or damage on account of delayed delivery of goods and since, mere delay in supplies was unlikely to cause damages, question of even fixing a reasonable compensation under Section 74 of Indian Contract Act, 1872 ('ICA') did not arise. Consequently, MTNL was asked to refund HTL sum of Rs. 1,03,20,763 together with interest @ 12% from the date of Award till the date of payment.

In present case, it is not possible for Court to agree with submission on behalf of HTL that, MTNL was required to prove actual loss suffered by it. Purpose of first part of Clause 16.2 is to provide for a genuine pre-estimate of damages payable as LD even without requirement of having to prove actual loss. Section 74 of ICA emphasises that, in case of a breach of contract, party complaining the breach is entitled to reasonable compensation whether or not actual loss is proved to have been caused.

In present case, AT proceeded on erroneous basis that, first part of Clause 16.2 required proof of actual loss. In fact, first part of said clause applied only where "delayed portion of supply does not in any way hamper commissioning of system." If it did, then second part of Clause 16.2 applies. Very interpretation of Clause 16.2 and of Section 74 of ICA by AT was, therefore, flawed.

Specifically, AT has overlooked legal position as explained in ONGC v. Saw Pipes Limited and, in particular, its observation that "in some contracts, it would be impossible for Court to assess compensation arising from breach and if compensation contemplated is not by way of penalty or unreasonable, Court can award same, if it is genuine pre-estimate by parties as measure of reasonable compensation." Conclusions of AT that: "Forfeiture of part of price is out of all proportion to damage" and that "It is unconscionable for purchaser to retain and withhold part of price" is not on basis of analysis of pleadings or evidence. Specifically, plea of MTNL that it purchases materials from several sources and "delay caused by one of suppliers by itself cannot be pleaded and proved" and, therefore, present case "falls within that class where Court may not be able to assess compensation on account of breach of contract to supply some material" was not even discussed by the AT. Purport of HTL's letter No. Nil dated 6th May, 1995 to MTNL stating that, it was ready to "accept price and L/d as acceptable to MTNL" was also not examined.

Interpretation of Clause 16.2 by AT is such that, no fair minded or reasonable person would adopt in facts and circumstances of case. Impugned Award is also contrary to settled legal position as regards Section 74 of the ICA. Consequently, impugned Award is set aside on ground that, it is contrary to provisions of contract, the ICA and also opposed to fundamental policy of Indian law as explained in decisions of Supreme Court. MTNL is not liable to return sum claimed from it by HTL.

Comments

Popular posts from this blog

MACT - Permanent disability - calculate - compensation - Supreme Court - Part 2

1) C. K. Subramonia Iyer vs. T. Kunhikuttan Nair - AIR 1970 SC 376 2) R. D. Hattangadi vs. Pest Control (India) Ltd. - 1995 (1) SCC 551 3) Baker vs. Willoughby - 1970 AC 467 4) Arvind Kumar Mishra v. New India Assurance Co.Ltd. - 2010(10) SCALE 298 5) Yadava Kumar v. D.M., National Insurance Co. Ltd. - 2010 (8) SCALE 567) 5. The heads under which compensation is awarded in personal injury cases are the following : Pecuniary damages (Special Damages) (i) Expenses relating to treatment, hospitalization, medicines, transportation, nourishing food, and miscellaneous expenditure. (ii) Loss of earnings (and other gains) which the injured would have made had he not been injured, comprising : (a) Loss of earning during the period of treatment; (b) Loss of future earnings on account of permanent disability. (iii) Future medical expenses. Non-pecuniary damages (General Damages) (iv) Damages for pain, suffering and trauma as a consequence of the injuries. (v) Loss of amen

Distinction between “Loss to the Estate” and “Loss of Estate”

A subtle but fundamental distinction between “Loss of Estate” and “Loss to the Estate” was discussed in Omana P.K. and others v. Francis Edwin and others (2011 (4) KLT 952). This Judgment was challenged before the Apex Court, which has now dismissed the Appeal. The question raised in this case, was whether a certain sum which the dependants received as compensation for untimely death of Judgment debtor in a motor accident is attachable in Execution Proceedings. In this case, Justice Thomas P. Joseph speaking for the Kerala High Court had held the following (relying on The Chairman, A.P.S.R.T.C, Hyderabad vs. Smt. Shafiya Khatoon and Others) Capitalized value of the income spent on the dependents, subject to relevant deductions, is the pecuniary loss sustained by the members of his family through his death. The capitalized value of his income, subject to relevant deductions, would be the loss caused to the estate by his death. In other words, what amount the dependents would have got le

Full & Final payment - No dues certificate - end of contract

Whether after the contract comes to an end by completion of the contract work and acceptance of the final bill in full and final satisfaction and after issuance a `No Due Certificate' by the contractor Supreme Court of India Supreme Court of India R.L. Kalathia & Co. vs State Of Gujarat on 14 January, 2011 Author: P Sathasivam Bench: P. Sathasivam, B.S. Chauhan IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 3245 OF 2003 R.L. Kalathia & Co Appellant(s) Versus State of Gujarat .... Respondent(s) JUDGMENT P. Sathasivam, J. 1) This appeal is directed against the judgment and final order dated 07.10.2002 passed by the Division Bench of the High Court of Gujarat whereby the High Court set aside the judgment and decree dated 14.12.1982 passed by the Civil Judge, (S.D.), Jamnagar directing the State Government to pay a sum of Rs.2,27,758/- with costs and interest and dismissed the Civil Suit as well as cross objections filed by the a